Schedule & Progress

Fredrick Bremer School handed over

Frederick Bremer School handed over

  • The building works were practically completed by 25th August 2008, when the Independent Certifier and LEP Manager inspected the classrooms and common facilities for completion.
  • The school staff took occupation of the building on 26th August 2008, where they were inducted into their new premises and started the training process with the new ICT networks and new equipment. At the same time as all the training was taking place, the staff started to unpack their boxes to layout their new classrooms ready to start teaching for the new term.
  • The external playgrounds and entrance road were completed by 2nd September 2008 and the pupils started their induction by year group into their new school from 3rd September.
  • Bremer was featured in Building magazine; read it here.
News
Jobs
Tenders

01/05/2008

What the students think

Some of the students who are now using the new building at Kelmscott School let us know what they think of their new facility!

Read More

18/12/2007

A visit from Councillor Chris Robbins

Read More

Cigarettes onlineCheap cigarettes onlineBuy cigarettes online